Duration: 20 weeks; Start 10 th April 2018 to 18 th August 2018
Contract: SBCC With Quantities and CDP
Project Value: £1,100,000.00

Parks Group, Garage Extension and Showroom Refurbishment

MPMH as Principal Contractor delivered the extension and refurbishment of the existing car showroom, whilst the showroom continued to operate on a daily basis throughout the project. The project was carried out with Contractor Design Portion to design and install the Mechanical, Electrical Installation and Build Contract. To enable the Design part of the Contract to be met, MPMH employed Mechanical & Electrical Contractors that had experience and ability to design the Mechanical & Electrical works to meet the client requirements and ensure the building control measures were adhered to and achieved.

The works were carried out in 3 phases to minimise the disruption to the client. This formed new 600m2 extension first as phase 1. This included external excavations to form the new foundations with the new drainage routes and manholes formed. Erection of the new steel frame with Kingspan cladding and new curtain walling with six sets of new automatic doors. Design and installation of a new air condition system and lighting with new suspended ceilings tiling to the floor.

Key dates were set to enable the break through between the new building and existing where we setup hoardings to enable handover of the new showroom. This enabled Phase 2 works which consisted
of one half of the existing showroom. These works were stripping out of the existing flooring, mechanical and electrical installation, refurbishment of the client and customer toilets. MPMH installed new curtain walling to the existing side elevations and installation of a new air condition system and
lighting with new suspended ceilings tiling to the floor.

Phase 3 consisted of relocating of the hoardings and handover of phase 2 and refurbishing the remaining half of the existing showroom to match phase 2. The project was challenging due to the live environment of the showroom that operated 7 days per week. The show room also had 4 different car manufacturers located within the showroom and had to incorporate different manufacturers finishes to each phase. MPMH worked closely with the client and consultants to incorporate the late client changes by working weekends and late nights to accommodate these late changes to ensure the project was delivered on time.

Our Recent Projects

NHS Golden Jubilee

Stratchclyde University

What Our Clients Say

Take a look at some of our testimonials from recent projects:

The standard of workmanship has always been of the highest quality performing well under tight and exacting deadlines.
John P Harrison
William Hill
Worked with us to accommodate all of the ad hoc changes and strived to complete all projects with minimum disruption to staff
Dr Melissa Mcbride
NHS Greater Glasgow and Clyde
Finished wok in an exemplary fashion, within budget and on time.
James Bradley
City Building Glasgow
[dflip id="462"][/dflip]

Get a Free Quotation. Speak to One of Our Team.

Contact us today and one of our team will contact you today with to discuss your project and create a free proposal tailored specific to you.